Pipers Hill Primary School

Services:

Commencing on site in March 2008, P.Elliott delivered the three elements that comprise the €20 million Pipers Hill Education Campus (Gael Scoil, Sports Hall and Post Primary School) on time after a 74 week programme. Prior to commencing on site, the team decided to replace the ‘traditional’ block work element of the scheme with precast units.

 

 

 Pipers Hill Primary School

 

 

Though cost neutral, this modification aided the timely delivery of the scheme for the clients Kildare VEC. Having worked with the design team and nominated subcontractors throughout the scheme, Stroma carried out the final air permeability tests and all three structures achieved the target air leakage rate of 5 m3/(m2.hr) @50Pa.

 

Pipers Hill Primary School Case Study – download