Stroma was appointed to carry out a series of site inspections, all supported with illustrated reports, designed to monitor the implementation of the air barrier on a floor by floor basis.

 

northwood800x400

 

Air Tightness Testing in Ireland

With an air tightness target of 7 m3/(m2.hr) @50Pa, attention to detailing and the specification of robust materials within the air barrier was given due care.  When testing of the building took place, the building achieved a figure of 6.39 m3/(m2.hr) @50Pa.

 